Contracts for Difference (CfD)

Also known as: offshore wind farm, floating wind, wind at sea, marine wind farm, wind turbine offshore, offshore wind power

A Contract for Difference is the UK's main subsidy mechanism for large-scale low-carbon electricity. Generators win contracts in competitive auctions and are then paid the difference between an agreed 'strike price' and the market price for every unit they produce — topped up when prices are low, paying money back when prices are high — giving projects stable, inflation-linked revenue for 15 to 20 years.

What it is

The Contract for Difference (CfD) is the UK government's primary mechanism for supporting new large-scale low-carbon electricity generation. It stabilises a generator's revenue around a fixed, inflation-indexed "strike price" for the life of the contract — historically 15 years, extended to 20 years for offshore wind, onshore wind and solar from Allocation Round 7. Because it removes wholesale price risk, the CfD is what makes multi-billion-pound projects like offshore wind farms bankable.

How it works

A CfD is a private-law contract between a generator and the Low Carbon Contracts Company (LCCC), a government-owned counterparty. The mechanism has four moving parts:

  1. Strike price. The price per MWh the generator is guaranteed, set competitively at auction and indexed to inflation (published in both 2012 and current-year prices on GOV.UK).
  2. Reference price. A measure of the prevailing wholesale market price for the relevant period.
  3. Difference payments — in both directions. When the reference price is below the strike price, the LCCC tops the generator up to the strike price. When the market price is above it, the generator pays the difference back. This two-way design is what distinguishes a CfD from a simple subsidy.
  4. Funding. Difference payments are funded through a statutory levy on licensed electricity suppliers (the Supplier Obligation), which ultimately flows through to consumer bills — and flows back when generators are paying money in.

Contracts are awarded through allocation rounds: sealed-bid, pay-as-clear auctions run by NESO as Delivery Body, with DESNZ setting the budget and rules. Technologies compete within "pots" — established technologies such as onshore wind and solar in Pot 1, emerging technologies like tidal stream and geothermal in Pot 2, offshore wind in Pot 3, and floating offshore wind in Pot 4. Each technology has an Administrative Strike Price acting as a bid ceiling; competition then drives the clearing price down. Winners sign with the LCCC and must hit milestone and delivery-year commitments or risk losing the contract.

Why it matters in procurement / cleantech

The CfD is not itself a public tender in the procurement-law sense — it's a revenue support scheme — but it is the single biggest demand driver in UK clean generation, and every allocation round triggers a wave of real procurement downstream. Developers who win CfDs immediately go to market for EPC contracts, turbines, cables, foundations, vessels, port infrastructure, grid connection works and long-term O&M. For suppliers, the published results (project names, capacities, delivery years) are effectively a forward pipeline of contract opportunities with known timing.

The scale is significant. Allocation Round 7, whose offshore wind results were published on 14 January 2026, secured a record 8.4 GW of offshore wind — the largest single offshore wind procurement in UK and European history — at clearing prices of £91.20/MWh (England/Wales) and £89.49/MWh (Scotland) in 2024 prices, with floating offshore wind clearing at £216.49/MWh. The AR7a round (Pots 1 & 2) followed on 10 February 2026, adding roughly 6.2 GW — around 4.9 GW of solar, 1.3 GW of onshore wind and 20.9 MW of tidal stream — bringing AR7 to ~14.7 GW overall. AR7 also introduced the Clean Industry Bonus, an additional payment rewarding offshore wind developers that invest in sustainable UK supply chains — a direct hook for domestic manufacturers and service providers.

For buyers and investors, the CfD also sets the benchmark commercial model against which alternatives — merchant operation, corporate PPAs, or hybrid structures — are judged. Storage co-located with CfD generation must be carefully metered and structured, since CfD payments apply only to the supported generation.

Key considerations / variants

  • Contract length changed at AR7. Terms were extended from 15 to 20 years for fixed and floating offshore wind, onshore wind and solar — a major shift in project economics that analysts credit with enabling lower bids. Older contracts (AR1–AR6) remain 15-year.
  • AR7 split the round in two: AR7 for offshore wind technologies and AR7a for everything else, each with its own timeline and budget.
  • Eligibility was relaxed for offshore wind: projects could bid while still awaiting full planning consent, provided their Development Consent Order application had been accepted for examination at least 12 months earlier.
  • Locational signals are emerging. AR7 used separate clearing prices for offshore wind depending on the Scottish/non-Scottish transmission charging zone — a precedent for embedding locational investment signals in the CfD.
  • Negative pricing rule: difference payments are not made during extended periods of negative wholesale prices, so generators carry some merchant exposure at the margins.
  • The scheme keeps evolving. A consultation on Allocation Round 8 reforms opened in December 2025, and Clean Industry Bonus regulations were updated ahead of AR8 in February 2026 — always check the official CfD allocation round microsite and GOV.UK for the live rules before bidding.

Related

[capacity-market] · [power-purchase-agreement] · [long-duration-energy-storage] · [floating-offshore-wind] · [green-hydrogen]

how does a contract for difference work
what is a CfD in renewable energy
what is a strike price
how do CfD auctions work in the UK
what happened in allocation round 7
are CfD contracts 15 or 20 years
who pays for CfDs
how do I bid for a CfD
what is the Clean Industry Bonus
capacity market power purchase agreement long duration energy storage floating offshore wind green hydrogen

Explore CfD-backed tenders

Explore CfD-backed tenders

Last reviewed: 11 June 2026