Also known as: capacity auction, T-4, T-1, capacity mechanism, mercato della capacità
The Capacity Market is the UK's main mechanism for ensuring electricity security of supply. Generators, battery storage, demand-side response providers and interconnectors compete in annual descending-clock auctions to win Capacity Market Agreements — fixed payments in return for committing to deliver capacity during periods of system stress.
The Capacity Market (CM) is a UK government mechanism, introduced in 2014 under Electricity Market Reform, designed to guarantee that Great Britain's electricity system has enough reliable capacity to meet peak demand — even as intermittent renewables grow. Rather than paying for energy generated, the CM pays providers for being available to deliver power (or reduce demand) when the system is under stress. Generators, battery storage systems, demand-side response (DSR) providers and interconnectors all compete in annual auctions for Capacity Market Agreements, receiving a steady, predictable revenue stream in exchange for a legally binding commitment to perform when called upon.
The CM operates through two annual auctions, both administered by the National Energy System Operator (NESO) as Delivery Body.
T-4 auction. Held four years ahead of the delivery year, this is the main procurement event. DESNZ, informed by NESO's demand and reliability forecasts, sets a target volume of capacity. The auction runs as a descending clock: it opens at the price cap (currently £75/kW/year) and drops in £5/kW increments each round. Participants either remain in or exit at the minimum price they are willing to accept. When remaining capacity falls to the target, the auction clears and every remaining bidder wins a Capacity Market Agreement at that single clearing price.
T-1 auction. Held one year ahead, this tops up volumes in light of updated demand forecasts and any changes in available capacity since the corresponding T-4. Only one-year agreements are awarded in the T-1.
Agreement lengths. Existing plant typically receives one-year agreements. New-build projects that meet capital-expenditure thresholds can secure multi-year agreements — up to 15 years for high-capex builds, up to nine years at the mid-tier threshold introduced for the 2029/30 round, and up to three years for low-carbon units with zero capex.
De-rating factors. Not all capacity is equally dependable, so NESO applies technology-specific de-rating factors. These convert nameplate capacity into a "de-rated" figure reflecting realistic availability during stress events. For battery storage, the factor depends on discharge duration — short-duration systems (e.g. 0.5-hour) receive very low factors, while systems of four hours or more receive substantially higher ones. Wind and solar are heavily de-rated (typically low single-digit percentages) because of intermittency.
Delivery obligations and penalties. During a delivery year (October to September), providers must demonstrate availability through Satisfactory Performance Days and respond during declared System Stress Events. Providers that fail to deliver their adjusted capacity obligation during a stress event face financial penalties, capped at 200% of the unit's monthly capacity payments. Those that over-deliver receive a share of the penalty pool.
Funding. Capacity payments are funded by a statutory levy on licensed electricity suppliers (the Capacity Market Supplier Charge), ultimately passed through to consumer bills.
The CM is one of the primary revenue underpinnings for flexible and firm-power assets in the UK. For battery storage developers, a multi-year Capacity Market Agreement provides a contracted floor revenue that supports project finance alongside merchant trading, ancillary services and wholesale arbitrage. In the most recent T-4 auction (for delivery in 2029/30), batteries secured around 1.2 GW of de-rated capacity, with longer-duration four- and five-hour systems increasingly prominent. DSR providers — aggregators, industrial sites and EV charging operators — also compete, and together DSR and storage now routinely account for a significant share of awarded capacity.
For EPC contractors, O&M providers and equipment suppliers, each auction round's published results reveal a forward pipeline: which projects won, their capacities, delivery years and, for new-build, the capex thresholds they met. The CM thereby functions as a demand signal for construction and supply-chain activity, much as CfD allocation rounds do in the generation sector.
[battery-energy-storage-system] · [contracts-for-difference] · [long-duration-energy-storage] · [virtual-power-plant] · [smart-grid] · [intermittency]
COMMON QUESTIONS
RELATED TERMS
Explore Capacity Market tenders
Explore Capacity Market tendersLast reviewed: 12 July 2026